Lower Playground - the lower (creekside) playground retrofit was completed at the end of July 2025
Upper Playground - the upper playground retrofit began on August 4th and is scheduled to be completed by August 18th
Creek Crossing - the reconstruction of the creek crossing is scheduled to begin on August 11th and will be completed in four to eight weeks. Please contract the office for further updates.
Ballfields - the ballfields will undergo improvements in 2025-2026
RV Park - the new nine space RV park should begin construction in 2026