Western Gateway Park Improvements
Lower Playground - the lower (creekside) playground retrofit was completed at the end of July 2025.
Upper Playground - the upper playground retrofit began on August 4th andwas completed by the end of August 2025.
Creek Crossing - the reconstruction of the creek crossing began on August 11th and was completed by the end of September 2025.
Ballfields - the ballfields will undergo improvements in 2025-2026
RV Park - the new nine space RV park should begin construction in 2026
Arch Sign - a community financed arch entrance sign is in the beginning stages. Contact the WGP Foundation for more information.
The park always needs volunteers! If you would like to get involved with park improvements, please call the office at 530.432.1990.